The 2011 Arterial and Collector Pavement Preservation project is scheduled to begin construction activities on Wednesday (Sept. 7) on Terrace Drive Northwest from R Street Northwest to W Street Northwest.
Construction is expected to last approximately one week. The work is weather dependent.
The working hours are weekdays from 7 a.m. to 6 p.m. During construction the road will remain open to traffic, but traffic will be reduced to one lane with alternating one-way traffic at times. Traffic delays should be anticipated.
The project will perform pavement patching on the street.
For further information, call the City of Auburn Public Works Department at 253-931-3010.